Frame delivered on a high-risk program of works, meeting all business requirements, with minimal disruption of services, no unplanned outages and zero rollbacks.
Frame was engaged to manage the service transition and integration. Success depended on a seamless delivery, enabling the airport to remain fully functional for the project’s duration.
With the incumbent’s contract due to expire at the end of November, transition to the new service provider needed to be completed by then for the airport to avoid paying double the support costs and to beat the IT change freeze over the busy Christmas – New Year period. This meant a high-risk program of works entailing in excess of 50 major cutovers in a live airport environment had to be completed within 4 months.